EXTERIOR STRUCTURE OCTOBER'98


Cranes and lifts are used by the various trades to complete activities on the upper exterior of the structure.. 
The masonry at the north wall was the first stage of brickwork to be completed. 
 The masons lay their bricks in front of the black waterproofing membrane that has been laid out for them.
Like other trades on this project, the masons work is flowing from north to south. 
 This worker uses a lift to work on the waterproofing of the masonry backup on the gymnasium.