Finishes/Punch-list
This is the stage where the
final inspection of construction work is conducted. The start of of closing out
of the project begins near the end of a project, when the contactor requests a
final inspection of the work. Before completion of the project, various
equipment, electrical systems, and mechanical systems must be ready for testing
and approval by the construction manager. A punch list is prepared
listing all items that need to be completed or corrected. To develop this punch
list, the field inspection personnel must carefully review their daily
inspector's log to note all work items which have been entered that require
corrective actions. The punch list is generally a list of tasks, or a "to-do"
items organized for the completion of a project.
Acceptance of the work and final payment to the contractor must be done in
accordance with the specification sin the contract documents. substantial
completion of a project is the date when the construction is sufficiently
complete in accordance with the contract documents so that the project can be
used for the purposes intended. 1